MIL-HDBK-965
5.1.3 Option C - Government guidance with as -built parts li st. The Government provides guidance and acts as an advisor, while requiring the contractor to provide an as-built parts list to the AA and MPCAG. See figure 3.
MPCAG
FIGURE 3. Option C - Government guidance with as -built parts list.
The following procedures are for use for successful implementation of option C:
a. The contractor should respond to RFPs by describing methods to reduce life cycle costs, achieve GIDEP participation, achieve parts standardization to minimize parts proliferation, and prevent DMS cases.
b. The AA monitors success of the program through contract language and scheduled periodic program reviews and interfaces with IPTs to assess the accomplishment of parts management goals and objectives and to discuss and resolve part problem areas/issues.
c. MPCAG will provide access to the GFBs to the contractor for part selection assistance.
d. The contractor may request advice from the AA and MPCAG on parts selections; however, the contractor has no obligation to request or to accept such advice. If MPCAG parts advice is requested, MPCASS is the preferred method of submitting the parts evaluation requests to the MPCAG.
e. The contract may require the contractor, or the contractor may elect, to establish a PCB, or the contractor may elect to do so.
f. The SOW should have a task and a data item to deliver an as-built parts list to the AA and the
MPCAG in accordance with the contract.